​Flight Rail Blog

Building The Full-Scale Guideway Truss

1/19/2016

0 Comments

 
Picture
Picture
Rainy weather has kept us indoors, but we have lots to do! Our dedicated team of 3 welders/fabricators has begun assembling a 20-foot full-scale section of curved guideway truss. This will enable us to refine the full-scale construction sequence and provide a structure for experimenting with full-scale power tube designs and materials. The power tube will be supported inside of the uprights shown in the photos. The outside horizontal sections at the top of the Z-supports will provide for catwalks on both sides of the rails. At full scale, this structure would be elevated an average of 14 feet on pylons. ​
0 Comments

Construction progress on the curve

12/5/2012

0 Comments

 
Picture
Picture
Picture
We are making progress on building and installing the final 895 feet (272.98 m) of our outdoor test guideway. The pictures below show the progression in 2012 and the installation of 400 feet (122 m) of guideway. The curved section is a 180° banked curve with a 48 foot (14.64 m) radius. This equates to a full size train operating on a 262 foot (79.91 m) radius or 22° curve. The final 495 feet (150.98 m) - soon to be installed - includes a few straight sections to connect the 2%, 6%, and 10% grades to the curve, curve sections, and straight sections that follow the curve. This will complete the guideway project with a total length of 2095 feet (638.98 m).  ​
0 Comments

Relocation of second power station

6/14/2012

0 Comments

 
Picture
We moved the second power system next to the original power system while installing the additional guideway. We now have pull/pull and push/push capabilities.
0 Comments

New control tower

8/15/2011

0 Comments

 
Picture
We just completed the control tower to more easily operate and view the VECTORR. With the guideway 1200 feet (366 m) long and an additional 700 feet (213.50 m) coming soon, we needed to have a better vantage point above the grapevines to view the entire guideway. VECTORR is currently operated by remote control. We now have power at the tower and plans to install a control panel in the tower to operate VECTORR. Our demo guests are enjoying this new addition to our test facility.
0 Comments

New G-valve installed

6/17/2011

0 Comments

 
We now have the gate valve (G-Valve) installed that automatically closes off the east end of the power tube. This valve enables push-pull on the 10% and 2% grades whenever VECTORR is on the guideway between the two power systems. When the VECTORR is on either side of the power systems, we can use push-push or pull-pull which more than doubles our top speed capability.
0 Comments

Benefits of second power station

5/24/2011

0 Comments

 
Picture
Today we operated the newly installed second power system that is located on the west end of the guideway. We ran the VECTORR first with only the new power system to compare it to the original one that is located towards the eastern end of the guideway. We then tested with both systems running. As expected, performance and speed increased dramatically. Now, using push-pull, VECTORR climbs the 10% grade more easily than it did the original 6% grade. From the base of the 10% grade, VECTORR accelerated so rapidly that it reached the maximum speed we allow on the track by the time the entire unit crested the grade. The push-pull is utilized as a form of "atmospheric boost" to maintain respectable speeds on steep grades. The guideway is now 1200 feet (366 m) long. A video showing push-pull on the 10% grade can be found on the Photos and Videos page. The western power system was pushing while the eastern power system was pulling the unit over the 10% grade.     ​
0 Comments

Guideway lengthening

3/7/2011

0 Comments

 
Picture
The guideway is now 1000 feet (305 m) long. The pictures below show the 10% grade leveling off and transitioning to a 2% grade. An additional 700 feet (213.50 m) of guideway, a second stationary power system, and a Z-Valve will be installed by Fall 2011. The pilot model final phase is to extend the guideway to include a 180 degree curve with a 48 foot (14.64 m) radius.
0 Comments

Addition of 10% grade to guideway

7/15/2010

0 Comments

 
Picture
The extension of the outdoor test guideway is currently under construction. We are adding 1100 feet (335.50 m) to the existing guideway shown below to include a 10% grade. This will allow us to further document the grade climbing and atmospheric braking capabilities of VECTORR.
0 Comments

    Archives

    August 2024
    July 2017
    June 2017
    February 2017
    September 2016
    August 2016
    January 2016
    September 2015
    February 2015
    December 2014
    April 2014
    December 2013
    January 2013
    December 2012
    October 2012
    June 2012
    January 2012
    August 2011
    June 2011
    May 2011
    March 2011
    July 2010

    Categories

    All
    Community
    Construction
    Corp Development
    Media
    Protoype

    RSS Feed

THIS PROJECT IS NO LONGER ACTIVE: SITE FOR ARCHIVE PURPOSES ONLY
​We are not open to the public

​[email protected] 
Site ​copyright Flight Rail Corp. 2017